[Latest Pictures]

[Motorists Fuming]

[Frenches Road Closure] [January 2005]

[28th December 2004] [ 27th December 2004 ]

[ Christmas Day & Boxing Day ]

[Schedule of Work]

Updated 26th January 2005

Spectators Watch As Bridge Goes In
Surrey Mirror 12th January 2005

 The long-awaited underbridge that will eventually give access to the Holmethorpe industrial estate and the new 500-home Mere Park housing estate, has gone in.
About a dozen spectators turned up to watch as the 1,650 tonne concrete box bridge, travelling at one mile an hour, was edged into a gap cut into the railway embankment.
It had taken about 20 years of negotiations and planning, and the scheme, costing Linden Homes £10m, had reached a critical milestone.
Catherine and Malcolm Walker, from Linkfield Lane, Redhill, were there to watch.
Mr Walker, a builder, said: "It was absolutely brilliant, a wonderful piece of technology and workmanship. It's going to make a lot of difference to the area."
Clive Robinson, 37, from Colesmead Road, Redhill, said: "I wanted to see the bridge being moved into position."I saw it being built from the beginning and it's just a fascinating piece of engineering."
The operation took place on Boxing Day.The main contractor for the bridge project was Hochtief (UK) Construction Ltd.
Andrew Richards, director, spoke of the challenge they faced. He said: "We had 102 hours in which to cut away the embankment, position the bridge, infill the embankment, reinstall the track and rail lines, and reroute the signals and power cables. "It was a great challenge and, in my opinion, a spectacular achievement."Construction of the estate access road will start in February.

The Bridge so Far
Surrey Mirror 16th December 2004


The Bridge, part of the new Holmethorpe Regeneration Programme, is now ready to be moved into place over the Christmas period.

The installation is scheduled to begin very late on Christmas Eve, continuing until dawn on Wednesday 29th December, although if any unforeseen problems are encountered, the operation may take an extra day.

Close to the bridgeworks there will be floodlights, and some unavoidable noise may be experienced, as well as earthworks traffic.

In the region of 25 households in the immediate area have accepted Linden Homes invitation of alternative accommodation for the duration of the necessary work.

As from Christmas Eve they will move to the Copthorne Hotel for five nights, and each family will also receive £250 spending money.

The earthworks programme will consist of the removal of 34,000 tons in the space of four days, and in the interest of health and safety some parts of Battlebridge Lane, Frenches Road (north of Trowers Way) Trowers Way and Ormside Way will be closed to thorough traffic.

Parking and waiting will be restricted, although buses, residents and pedestrians will be allowed through. Advance warning signs and diversionary routes have been posted in the immediate area.

After Christmas there will be some unusual works taking place on Sunday January 2 and Sunday January 9, but these will be no more intrusive than previous.

The road closures will end on Thursday December 30, but return in Mid January.

This further restriction will leave Fairhaven Road closed at its eastern end, and Frenches Road closed (except for buses and access for residents) from the Jolly Brickmakers pub to the junction with Battlebridge Lane.

Battlebridge Lane will remain open (with traffic control) while services and traffic signals are installed. This second phase of the programme will remain in operation until the new relief road is opened in the summer of 2005.

Anyone with questions about the overall programme may contact the 24-hour helpline on 08700 781000.

 


January 2003 saw the plans for a much needed relief road into the Holmethorpe Industrial Estate come under public scrutiny. This immediately brought fervent opposition from South Merstham residents to sections of the proposals for the new road.

Those who saw the plans, which had been released by Surrey County Council for public consultation, were dismayed at some of the aspects of the report. They considered them to not only be detrimental to South Merstham’s community, but also cause an unnecessary diversion for residents travelling to Redhill making them travel via New Battlebridge Lane and onto the already busy A23

 


Holmethorpe work has started
News bulletin dated 9 September 2004
about the Holmethorpe Regeneration Project taking place in Redhill. Work on the long-awaited regeneration of Holmethorpe has begun.

 

The regeneration includes :-
• Building a new road to stop heavy lorries using residential roads to access Holmethorpe Industrial Estate;

• Building a new housing development, to be named Mere Park, providing over 400 new homes. Mere Park, which is funding the new road, will provide a mix of housing of which 30 percent will be social and starter housing.

• Major environmental improvements including provision of public open space and a creation of a wetland bird nature reserve.


• Closure of the quarry and sand drying plant in 2005 which will considerably reduce air pollution and sand lorry movements in the area.


The Council and the developers working on the project have made a huge effort to ensure that the work causes the least possible inconvenience to residents.
Due to the logistics of the project, the work will have an impact on the lives of some residents living in the immediate vicinity, and we have written to those residents explaining exactly what is happening and why.
We have also set up a 24 hour information line to answer all residents' queries.
New rail underbridge
From now until January 2005 a new bridge under the Redhill line is being built to take the new road from Ormside Way (on Holmethorpe industrial estate) to Frenches Road.
This work will be a major construction project, and the safety of the railway is of paramount importance.
It would not be practical to dig through the embankment while the railway is operational, and to either remove a section of the embankment to erect the underbridge in situ, or dig a tunnel would involve a lengthy closure of the rail lines. This would never to permitted by Network Rail.
The only solution is to build the new underbridge adjacent to the embankment and then roll it into place.
Noise levels
We are sensitive to the fact that this project is being carried out close to residential areas and are working with the developers Linden Homes and their contractors Hochtief to do everything possible to reduce noise.
The building of the underbridge adjacent to the embankment will not in itself be noisy.
However, there will have to be some noisy work and regrettably, some weekend, 24 hour and night-time working. This is so we can access the railway when the trains aren’t operating.


 

Holmethorpe Schedule of Works

Information about the schedule of works due to take place at Holmethorpe industrial estate.

The main elements of the installation of the under bridge connecting Frenches Road and Ormside Way are described below together with dates that the work will occur. 

The only Sunday working in the period up to Christmas will be on Sunday 26 September and Sunday 5 December. At Christmas there will be continuous working from Friday 24 to the morning of Wednesday 29 December.

There will some Saturday working with the remainder of the work being weekday working.  

Construction of an Access Ramp

An access ramp is to be constructed on the Eastern side of the rail line (next to Ormside Way on the Holmethorpe Industrial Estate) to allow heavy machinery and materials to reach the top of the embankment as the embankment itself is too steep.

The ramp is made from graded stone that is brought in by road and gradually compacted.

Date of work

  • 13 Sept - 1 Oct 2004.

Cable Diversion

The power cable runs alongside the rail line on the Frenches Road side of the site.   A temporary diversion cable will be laid, the existing power cable cut and then the supply connected to the diversion cable.

This work method is permitted by Network Rail.

Date of work

  • Sunday 26 September 2004 

Building a Track and Signal Cable Suspension Bridge

During the Christmas period the rail line and a stretch of embankment will be removed. Network Rail do not permit the track and signalling cable that runs alongside the rail line to be moved and so this must remain in place.

The cabling cannot support its own weight when the embankment is removed so a temporary suspension bridge will be constructed to support it. 

This will comprise two towers between which a suspension cable is slung that will hold the track and signal cables in place.

Date of work

  • Piling: Sunday 26 Sept (7am to 7pm) then weekdays to 8 Oct 2004.

  • Base Finishing: 7-15 Oct 2004

  • Erect cable bridge: Sunday 5 December 2004 

Building the New Bridge

Reinforcement bars are fixed into place to form the skeleton of the bridge around which plywood is placed to contain and provide shape to the concrete when it is poured in.

The plywood is open at the top to allow for the pouring of concrete. The concrete is brought in by road and placed in a skip which is lifted by crane over the opening.

The concrete is released into the plywood shuttering through a door in the base of the skip.   A vibrating poker is used to consolidate the concrete. The bridge is formed and cast in sections.

Date of work

  • Erect reinforcement and wood shuttering for sections: 6 September to 27 October 2004

  • Concrete pours – average of once a week - 6 September to 27 October 2004

Installing the Under Bridge

The under bridge   (which is separate to the cable bridge) will be installed by removing the rail lines, excavating the embankment, lifting the concrete box into the gap, rebuilding the embankment around the concrete box and then reinstating the rail lines.

Date of work

  • Continuously from 11pm on 24 Dec 4am - 29 December 2004.

 

Photographs: Sue Austen

Christmas Eve 2004

The new underbridge turned 90 degrees ready for lifting into place over the Christmas holiday

Track and Signal Cable Suspension Bridge seen from Subrosa

December 5th 2004

November 2004

October 2004

September 2004

August 2004

July 2004

March 2003

Pictures: Sue Austen

71888